Lookahead Planning & Daily Records
The master programme says what should happen; the lookahead decides what will happen in the next few weeks. Tasks only start well when their constraints are removed before the crew arrives, and only a good daily record shows later what really happened.
The lookahead
- A rolling 3-week (sometimes 6-week) lookahead breaks the next part of the programme into tasks by area and crew, updated every week.
- For each task, list the constraints: approved drawings, materials on site, RAMS and permits, manpower, access, inspections, the previous trade finished.
- Make-ready: only tasks with every constraint cleared go into next week's plan. Chase each pending item with a name and a date.
- Measure reliability: percent plan complete (PPC) = tasks completed as planned ÷ tasks planned. The Last Planner System uses it to find and fix the reasons for failure.
Daily site reports
- Record each day: weather and heat, manpower by trade, equipment, work done by area with quantities, delays and their causes, instructions received, visitors, safety events.
- Write facts, not opinions, and do it the same day. Daily reports are the first record anyone looks for in a delay or variation claim.
- Keep the manpower log and compare the actual histogram with the planned one; a gap is an early warning of delay.
Progress and reporting
- Measure progress by quantities or agreed weightings, not by feel.
- An S-curve compares planned and actual cumulative progress; earned value adds cost (see the earned value calculator).
- Report the critical path and near-critical activities first: they decide the completion date.
Use with this guide
Daily Site Report & 3-Week Lookahead
One-page daily report, manpower log with histogram, and a 3-week lookahead that shows which tasks are ready