Infrastructure Works: the Trades and How They Interface
An infrastructure package puts many trades into the same strip of ground and the same programme. Most delays come from the interfaces, not from any one trade.
The usual trades
- Earthworks and roads: excavation, fill, sub-base, asphalt, kerbs, markings.
- Wet utilities: storm water, foul sewer, potable water, treated sewage effluent (TSE) and irrigation.
- Dry utilities: MV / LV power, street lighting, telecom, ITS and traffic signals, often in duct banks.
- Structures: culverts, chambers, retaining walls, pump stations.
Where trades clash
- Gravity lines (storm, sewer) have fixed levels; lay them first and route pressure and dry services around them.
- Crossings: agree who goes over and who goes under, the clearance and any protection slab before digging.
- Manholes and chambers take space at junctions; draw them to scale in the combined services plan.
- Road layers need the trench backfilled and tested; plan the utility work before the sub-base, not after.
Making it work
- One combined utilities drawing with every service, its level and owner, kept current.
- A clash and crossing register reviewed weekly with all trade foremen.
- A sequence by chainage: deepest services first, then the shallower ones, then the road layers.
- Each utility owner's inspections booked in the look-ahead; their witness often sets the pace.