Cable Derating Factors
Tabulated cable ratings assume reference conditions. Real installations are hotter, more crowded or buried, so the rating is multiplied by correction factors.
The usual factors
- Ambient temperature (Ca): reference is 30 °C in air and 20 °C in ground. Gulf summers need factors for 45–50 °C.
- Grouping (Cg): cables bunched or laid together heat each other.
- Soil thermal resistivity: dry desert sand insulates far more than the 2.5 K·m/W reference.
- Depth of laying for buried cables.
- Thermal insulation where cables pass through insulated walls or roofs.
Applying them
- Multiply all applicable factors: Iz = It × Ca × Cg × …
- Size the cable so Iz ≥ In ≥ Ib (design current ≤ device rating ≤ derated capacity).
- Then check voltage drop and short-circuit withstand, which may force a larger size.