The Baseline Programme: What Consultants Check

The approved baseline is the yardstick for progress, delay and extension of time for the whole project. A weak baseline weakens every later claim.

What reviewers look for

  • Complete scope, contract milestones met without forced constraints.
  • Logic: every activity linked both ways; few leads, lags and hard constraints.
  • Realistic durations, calendars and resources; procurement and approvals included.
  • A clear critical path and sensible float.

Common quality checks

  • Many owners use a schedule health check based on the US DCMA 14-point assessment: open ends, leads, lags, relationship types, hard constraints, high float, negative float, long durations, invalid dates, resources, missed tasks, critical path test and critical path length index.
  • Run the same checks yourself before submission (Baseline Programme Before Submission checklist).

After approval

  • Freeze the baseline; update a copy each month.
  • Record any re-baseline and its approval in writing.
Good to knowSubmit a narrative with every baseline. Reviewers approve what they understand.