Good Scheduling Practice in Primavera P6 and MS Project

The software calculates dates from logic. Most programme problems come from settings and habits, not from the tool.

Settings to agree

  • Scheduling option for out-of-sequence progress (retained logic is the usual choice).
  • Calendars per activity type; one project default calendar.
  • Duration type and % complete type set the same way for all similar activities.
  • Critical path defined by longest path or total float, and stated in the narrative.

Habits

  • Link activities with logic; never type dates to make the bars look right.
  • Use milestones for key events and interfaces.
  • Keep activity names unique and readable: verb + object + location.
  • Save a copy before each update and compare.
Good to knowIf you have to type a date to make the programme look right, the logic is wrong.