PPM Compliance

Planned maintenance done on time, late or still open

Design data
%
ResultPreliminary · verify before design
PPM compliance (on time)85.0 %102 of 120 work orders
Over limitBelow the 95 % target by 10.0 points
Completion (on time + late)92.5 %
Completed late9
Still open (backlog)9
On-time work orders needed for the target114

Agree in the contract what 'on time' means (for example within the scheduled week, or ± 10 % of the interval) and whether statutory tasks (fire, lifts, water) are reported separately. They usually must be 100 %.

What to verify before design ↓

Verify before using in design

  • Report statutory and life-safety PPM (fire, lifts, water hygiene) separately: these are usually required at 100 %.
  • Check a sample of closed work orders on site: a closed ticket is not proof the task was done.
  • Check the edition of each standard that your project specification calls for.
  • Confirm with manufacturer data and the approved design before construction.
Basis & methodVersion 1.0 · Nov 2026Basis last checked: Nov 2026✓ Tested against worked examples

Formula

Compliance = on time ÷ scheduled × 100 Completion = (on time + late) ÷ scheduled × 100

Standards and references

  • EN 15341:2019 (maintenance key performance indicators)
  • ISO 41001:2018 (facility management systems: performance evaluation)

Assumptions

  • 'On time' means done inside the window agreed in the contract.

Inputs and units

PPM work orders scheduled1–100000
Completed on time
Completed late
Target compliance (on time)%50–100

Typical range: last column

Worked example (default values)

  • PPM work orders scheduled120
  • Completed on time102
  • Completed late9
  • Target compliance (on time)95 %
PPM compliance (on time)85.0 %Below the 95 % target by 10.0 points

Next steps