Fire Alarm Battery

Standby battery for a fire alarm panel

Design data
mA
mA
h
Settings & basis
ResultPreliminary · verify before design
Minimum battery capacity16.3 AhSelect 2 × 12 V 17 Ah (24 V)
Standby energy10.80 Ah
Alarm energy1.30 Ah
Alarm load de-rating factor D (BS 5839-1)× 1.75
Safety / ageing factor× 1.25

Simplified method. Use the panel manufacturer's battery calculation and any derating the standard requires; some authorities ask for 72 h standby.

What to verify before design ↓

Verify before using in design

  • Use the panel maker's battery calculation.
  • Use the one standard your project and local authority require. The options are separate design bases, not combined.
  • Some authorities require longer standby (e.g. 72 h).
  • Check the edition of each standard that your project specification calls for.
  • Confirm with manufacturer data and the approved design before construction.
Basis & methodVersion 1.1 · Nov 2026Basis last checked: Nov 2026✓ Tested against worked examples✓ Reviewed by an electrical engineer · Nov 2026

Formula

C = 1.25 × (T1 · I1 + D · T2 · I2) D = 1.75

Standards and references

  • BS 5839-1:2017
  • NFPA 72 (2022)
  • EN 54-4 (power supply equipment)

Assumptions

  • Constant standby and alarm currents; factor covers ageing and temperature.
  • BS 5839-1: the alarm load is multiplied by D = 1.75 because batteries give less capacity at the high alarm current.

Inputs and units

Design basis—
Standby (quiescent) currentmA
Alarm currentmA
Standby timeh24–72

Typical range: last column

Worked example (default values)

  • Design basisBS 5839-1 · 24 h standby + 30 min alarm × 1.75, total × 1.25
  • Standby (quiescent) current450 mA
  • Alarm current2600 mA
  • Standby time24 h
Minimum battery capacity16.3 Ah

Next steps

More ELV calculators

Found an error? Tell us

Describe the problem briefly (the wrong value, the right one, and the reference if you have it). The page name is sent automatically.