Asphalt Quantity & Trucks

Tonnes, truck loads, tack coat and paving days

Design data
m
m
mm
t/m³
%
t
L/m²
t/day
ResultPreliminary · verify before design
Asphalt required442 t3,650 m² × 50 mm at 2.35 t/m³ + 3 %
Area3,650 m²
Compacted volume182.5 m³
Truck loads18
Tack / prime coat1,095 L
Paving days at this output1.0

Use the compacted density from the approved mix design (job mix formula). Tack and prime rates and the layer thickness come from the project specification.

What to verify before design ↓

Verify before using in design

  • Confirm density, thickness and tack or prime rates with the approved job mix formula and specification.
  • Check plant capacity, haul time and laying temperature limits before planning daily output.
  • Check the edition of each standard that your project specification calls for.
  • Confirm with manufacturer data and the approved design before construction.
Basis & methodVersion 1.0 · Nov 2026Basis last checked: Oct 2026✓ Tested against worked examples

Formula

Tonnes = L × W × t × ρ × (1 + wastage)

Standards and references

  • Project specification (e.g. the QCS 2024 roadworks section in Qatar)
  • BS EN 13108-1 (asphalt concrete mixtures)
  • Asphalt Institute MS-22 (construction of HMA pavements)

Assumptions

  • Thickness is the compacted layer thickness; density is the compacted (in-place) density from the mix design.
  • Wastage covers thickness tolerance, edges and losses.

Inputs and units

Lengthm
Widthm2.5–40
Compacted layer thicknessmm25–150
Compacted densityt/m³2.2–2.5
Wastage and tolerance%0–10
Truck payloadt
Tack / prime coat rateL/m²0.1–1.5
Paving outputt/day

Typical range: last column

Worked example (default values)

  • Length500 m
  • Width7.3 m
  • Compacted layer thickness50 mm
  • Compacted density2.35 t/m³
  • Wastage and tolerance3 %
  • Truck payload25 t
  • Tack / prime coat rate0.3 L/m²
  • Paving output800 t/day
Asphalt required442 t