Asphalt Works on Site
Good asphalt is decided at four points: the approved mix, the temperature at delivery, how it is rolled, and how the joints are made. The tests afterwards only confirm what happened on the day.
Before paving
- Approved job mix formula (JMF) from Marshall or Superpave mix design, plus a trial section to set the rolling pattern.
- Surface below is clean, dry, at the right level, and primed or tack-coated at the specified rate; the tack must break (turn black) before paving.
- Weather check: no paving in rain, and respect the specification's minimum surface and air temperatures and wind limits.
- Enough trucks, a working paver and rollers, and a planned stop if the plant stops.
Laying and rolling
- Check mix temperature on every truck against the specification limits; reject mix that is too cold or overheated.
- Keep the paver moving at a steady speed with a constant head of material to avoid waves.
- Rolling sequence: breakdown (steel roller), intermediate (pneumatic or vibratory) and finish (steel, static) while the mix is still hot enough.
- Joints: cut back or heat the edge, tack it, overlap and roll the joint first. Offset longitudinal joints between layers and keep them out of wheel paths where possible.
Testing and acceptance
- Cores for thickness and in-place density (as a percentage of the lab or Marshall density, e.g. 97–98 %; check the spec), at the specified frequency.
- Air voids, binder content and grading from plant samples.
- Surface regularity with a 3 m straightedge or a profilometer (IRI), and levels against the design.
- Skid resistance and texture on wearing courses where specified.
Common asphalt defects
| Defect | Likely cause |
|---|---|
| Rutting | Weak mix for the heat and traffic, high binder, poor compaction |
| Bleeding | Too much binder or tack, low air voids |
| Ravelling | Cold or overheated mix, low compaction, low binder |
| Segregation | Poor handling, paver hopper emptied too often |
| Open joint | Cold joint not cut back or tacked, rolled late |