When the BOQ, Specification and Drawings Disagree
On most projects the documents disagree somewhere: a cable size on the drawing differs from the BOQ, or the specification asks for a test the BOQ does not mention. How you handle it decides who pays.
First steps
- Check the order of precedence in the contract (agreement, conditions, specification, drawings, BOQ: the order varies).
- Check whether the BOQ item description refers to the specification or drawing (many BOQs say 'as specified' or 'as shown').
- Do not choose the cheaper reading yourself: raise an RFI with references and a proposed answer.
Missing or wrong items
- Re-measured contract: an item shown on the drawings but missing from the BOQ is usually measured and paid; follow the preambles.
- Lump sum: missing BOQ items are often your risk if the work is shown elsewhere; check what the BOQ status is.
- If the engineer's answer changes the work, it is an instruction: check it with the Is It a Variation? checklist and give notice.
Records
- Log the RFI, the answer date and the work affected with dates.
- Keep tender queries and answers: they are part of the contract basis on many projects.