When the BOQ, Specification and Drawings Disagree

On most projects the documents disagree somewhere: a cable size on the drawing differs from the BOQ, or the specification asks for a test the BOQ does not mention. How you handle it decides who pays.

First steps

  • Check the order of precedence in the contract (agreement, conditions, specification, drawings, BOQ: the order varies).
  • Check whether the BOQ item description refers to the specification or drawing (many BOQs say 'as specified' or 'as shown').
  • Do not choose the cheaper reading yourself: raise an RFI with references and a proposed answer.

Missing or wrong items

  • Re-measured contract: an item shown on the drawings but missing from the BOQ is usually measured and paid; follow the preambles.
  • Lump sum: missing BOQ items are often your risk if the work is shown elsewhere; check what the BOQ status is.
  • If the engineer's answer changes the work, it is an instruction: check it with the Is It a Variation? checklist and give notice.

Records

  • Log the RFI, the answer date and the work affected with dates.
  • Keep tender queries and answers: they are part of the contract basis on many projects.
Good to knowSend the RFI with your proposed answer and its cost and time effect. A clear proposal gets answered faster than an open question.

Use with this guide

ChecklistIs It a Variation?TemplateRequest for Information (RFI)
Free

Submittal & RFI Tracker

Two registers with status codes, due dates, days open and overdue flags

  • How to use
  • Submittal register
  • RFI register

Excel (.xlsx) · version 1.1 · revised 7 Nov 2026 · blank template · check it against your project specification

TopicVariation Orders: When You Are Entitled, and Optional ItemsTopicHow to Read a Bill of Quantities (BOQ)
Found an error? Tell us

Describe the problem briefly (the wrong value, the right one, and the reference if you have it). The page name is sent automatically.