Utility Corridors: Allocating Space for Services in a Road

Every road cross-section reserves a strip for each service. The road authority and the utility owners publish their own allocation; the designer fits the project into it.

How space is allocated

  • Services usually run in the verge or footpath, not under the carriageway, so they can be reached without closing the road.
  • Each service has a reserved strip (distance from the kerb or property line) and a depth band.
  • Deep gravity services usually sit in or near the carriageway, where their levels and falls allow.
  • Crossings of the road are made at right angles, in ducts or sleeves, with spare ducts for the future.

Separations to keep

  • Potable water above and away from sewers, to avoid contamination; the owner sets the minimum distance.
  • Power cables apart from telecom to limit interference, and from other services for heat and safe digging.
  • Clearances at crossings and between parallel services follow each owner's standard; take the larger when two differ.
  • Trees and landscaping kept away from ducts and pipes, or root barriers added.

On site

  • Survey existing services first; real positions often differ from record drawings.
  • Mark the corridor on the ground and keep it free of temporary works where possible.
  • Record final positions and levels for the as-built and the utility owner's records.
Good to knowWhen the record drawings and the ground disagree, believe the ground: trial-pit before you design around a service.

Use with this guide

CalculatorDuct Bank Size & ConcreteCalculatorCable Pulling Tension & Sidewall Pressure
Free

Utility Crossing & Clash Register

Every crossing and clash by chainage: services, levels, clearance check, owner, solution and status

  • How to use
  • Register
  • Register (SAMPLE)

Excel (.xlsx) · version 1.0 · revised 21 Nov 2026 · blank template with a filled sample · check it against your project specification

ChecklistDuct Bank & Manhole Before Concrete Pour
Found an error? Tell us

Describe the problem briefly (the wrong value, the right one, and the reference if you have it). The page name is sent automatically.