Taking Over, Defects Period and Final Account

The end of the works is not the end of the contract. Taking over stops delay damages and starts the defects period; the performance certificate and the final statement close the money.

Taking over (Clause 10)

  • Apply for the taking-over certificate when the works pass the tests on completion and are ready for use; minor outstanding work may not prevent it.
  • Taking over usually moves care of the works to the employer, stops delay damages and releases part of the retention.
  • Sections or parts may be taken over separately if the contract has them.

Defects notification period (Clause 11)

  • The employer notifies defects; you inspect, agree the cause and fix them in a reasonable time.
  • Defects caused by your work or design are at your cost; others may be paid as a variation.
  • The period may be extended for parts that could not be used because of a defect.

Closing

  • Performance certificate after the last defects period: it marks completion of your obligations.
  • Final statement with all amounts you consider due, within the contract period after the performance certificate.
  • Return of the performance security and the remaining retention.
  • Agree subcontract final accounts in parallel.
Good to knowApply for taking over in writing as soon as the works are ready. Delay damages run until the date in the certificate.