Taking Over, Defects Period and Final Account
The end of the works is not the end of the contract. Taking over stops delay damages and starts the defects period; the performance certificate and the final statement close the money.
Taking over (Clause 10)
- Apply for the taking-over certificate when the works pass the tests on completion and are ready for use; minor outstanding work may not prevent it.
- Taking over usually moves care of the works to the employer, stops delay damages and releases part of the retention.
- Sections or parts may be taken over separately if the contract has them.
Defects notification period (Clause 11)
- The employer notifies defects; you inspect, agree the cause and fix them in a reasonable time.
- Defects caused by your work or design are at your cost; others may be paid as a variation.
- The period may be extended for parts that could not be used because of a defect.
Closing
- Performance certificate after the last defects period: it marks completion of your obligations.
- Final statement with all amounts you consider due, within the contract period after the performance certificate.
- Return of the performance security and the remaining retention.
- Agree subcontract final accounts in parallel.