Suspension, Termination and Disputes: the Basics
These clauses are rarely used but have the largest effect when they are. Follow the contract steps exactly: a wrong step can turn your right into a breach. Take legal advice before acting; this page is general information only.
Suspension
- The employer may instruct suspension (FIDIC 8.9); protect and store the works and record the cost and time effect.
- The contractor may slow down or suspend after notice for serious non-payment (Clause 16), following the stated periods.
Termination
- By the employer for contractor default, usually after a notice to correct (Clause 15), or for convenience where the contract allows.
- By the contractor for serious employer default (Clause 16).
- Termination ends the work but not the accounts: valuation, payments, securities and claims continue.
Disputes route
- Claim and the engineer's agreement or determination first (Clauses 3 and 20).
- Dispute avoidance / adjudication board (DAAB) where the contract has one (Clause 21).
- Amicable settlement period, then arbitration or the courts as the contract and the law say.
- Keep working and keep records while a dispute runs, unless the contract says otherwise.