Suspension, Termination and Disputes: the Basics

These clauses are rarely used but have the largest effect when they are. Follow the contract steps exactly: a wrong step can turn your right into a breach. Take legal advice before acting; this page is general information only.

Suspension

  • The employer may instruct suspension (FIDIC 8.9); protect and store the works and record the cost and time effect.
  • The contractor may slow down or suspend after notice for serious non-payment (Clause 16), following the stated periods.

Termination

  • By the employer for contractor default, usually after a notice to correct (Clause 15), or for convenience where the contract allows.
  • By the contractor for serious employer default (Clause 16).
  • Termination ends the work but not the accounts: valuation, payments, securities and claims continue.

Disputes route

  • Claim and the engineer's agreement or determination first (Clauses 3 and 20).
  • Dispute avoidance / adjudication board (DAAB) where the contract has one (Clause 21).
  • Amicable settlement period, then arbitration or the courts as the contract and the law say.
  • Keep working and keep records while a dispute runs, unless the contract says otherwise.
Good to knowBefore any suspension or termination notice, check every step and time limit with a lawyer. A wrong notice can become your breach.