Every foundation decision starts with the ground investigation (GI). It tells you what the soil and rock are, how strong and compressible they are, and where the groundwater sits.

Field work

  • Boreholes with sampling and the Standard Penetration Test (SPT): the N-value is the number of blows for 300 mm.
  • Cone Penetration Test (CPT): continuous profile of cone resistance and friction, good for layering in soft soils and sands.
  • Trial pits for shallow foundations and to see the ground directly.
  • Rock coring with RQD (rock quality designation) where rock is found, common across the Gulf at shallow depth.
  • Groundwater level recorded during and after drilling; piezometers for long-term readings.

Laboratory tests

  • Particle size distribution and Atterberg limits for classification.
  • Moisture content, density and specific gravity.
  • Shear strength (triaxial, direct shear) and consolidation (oedometer) for design parameters.
  • Chemical tests: sulfates, chlorides and pH, critical in the Gulf where sabkha and saline groundwater attack concrete.

Reading the GI report

  • Check the borehole logs, the groundwater level and the recommended foundation type and bearing value.
  • Note the concrete exposure class recommended from the chemical results.
  • Confirm the investigation covers the actual building footprint and depth of influence.
  • If the design changes (deeper basement, heavier loads), ask whether more investigation is needed.

Typical SPT N-values (indicative)

SoilN-valueDescription
Sand0–4Very loose
Sand4–10Loose
Sand10–30Medium dense
Sand30–50Dense
Sand> 50Very dense
Clay< 4Soft or very soft
Clay8–15Stiff
Clay> 30Hard
Good to knowAsk for the chemical test results early. In the Gulf they often decide the cement type, cover and waterproofing for every buried element.