Setting Out & As-built Surveys
Setting out turns design coordinates into pegs, lines and marks the trades build from. As-built surveys do the reverse: they record what was actually built. Both need independent checks.
Setting out
- Work from the approved coordinates and the survey control; the setting-out drawing should list every point.
- Set out from one control point and check from another; check dimensions between set-out points against the drawing.
- Use offset pegs or profiles that survive excavation; mark gridlines clearly and protect them.
- Record every set-out point and its check in a setting-out log signed by the surveyor and the engineer.
Tolerances
- Tolerances come from the specification (for example position and level of anchor bolts, column grids, slab levels).
- The setting-out accuracy must be well inside the construction tolerance, typically a few millimetres for structural grids.
- Raise discrepancies between drawings (grids not matching dimensions) as RFIs before setting out.
As-built and volume surveys
- As-built surveys record positions and levels of structures, services and finished surfaces, especially buried services before backfilling.
- Volume surveys (before and after) support quantities and payments for earthworks and stockpiles.
- Deliver as-built data in the agreed format (CAD layers, coordinates, levels) with the control used.