Surveying

Datums, Grids & Survey Control

Every coordinate on a drawing belongs to a datum and a grid. Mix two systems and a building can be set out metres away from where the designer put it. The survey control report tells everyone which system the project uses.

Datums and grids

  • A horizontal datum fixes positions on the earth; a map projection turns them into flat grid coordinates (eastings and northings).
  • A vertical datum fixes heights, usually mean sea level through a national levelling network and a geoid model.
  • GNSS works natively in a global frame (WGS 84 / ITRF); converting to the national grid needs the official transformation.

In Qatar, Saudi Arabia and Egypt

  • Qatar: Qatar National Grid on the QND95 datum (Transverse Mercator), used for most onshore engineering work.
  • Saudi Arabia: the national geodetic reference frame KSA-GRF17 (aligned with ITRF2014 at epoch 2017.0), heights on KSA-VRF14, with the national CORS network (KSA-CORS) for GNSS.
  • Egypt: the Egypt 1907 datum with Transverse Mercator belts (Red, Purple and Blue) remains widely used; newer projects may use other frames.
  • Always use the system named in the contract and the survey control report; older projects may use different systems.

Control and scale factor

  • Primary control points are surveyed once, protected, and checked regularly; all setting out works from them.
  • Grid distances differ from ground distances by the combined scale factor (projection scale × height factor). Over long lines it matters.
  • Keep a control register with coordinates, levels, descriptions and photos; re-check control after any disturbance.
Good to knowAsk for the control report and a coordinate check of two known points before you set out anything. Most large setting-out errors are a wrong system, not a wrong measurement.