Securities, Guarantees and Insurances
Securities and insurances protect the parties if something goes wrong. Missing a deadline or letting one expire can stop payments or give the employer a reason to call it.
Securities
- Performance security (FIDIC 4.2): usually a bank guarantee for a percentage of the contract price, due within a set period after the letter of acceptance, kept valid until the works are complete and defects are made good.
- Advance payment guarantee (14.2): equal to the advance; reduces as the advance is recovered from interim payments.
- Retention (14.3, 14.9): a percentage held from each payment up to a limit; often half released at taking over and half after the defects period; sometimes replaced by a retention guarantee.
- Parent company guarantee or other securities if the contract asks.
Insurances (Clause 19)
- Works and equipment (contractor's all risks): the works, materials and plant until taking over.
- Third-party liability: injury and damage to others.
- Employees: workers' compensation as the law requires.
- Professional indemnity when the contractor designs.
- Check who arranges each one, the amounts, the deductibles and the evidence deadline.
Keep control
- Put every security and policy in the Contract Abstract & Obligations Register with its expiry date.
- Extend before expiry; an expiring guarantee can be called by the employer.
- Ask for release and return on time at each stage.
Use with this guide
Contract Abstract & Obligations Register
One page of key contract data (dates, amounts, delay damages, retention, advance, securities, insurances) with worked-out dates, and a register of every obligation with clause, deadline and overdue warnings
- How to use
- Abstract
- Obligations
- Abstract (SAMPLE)
- Obligations (SAMPLE)
Subcontractor Register & Payment Tracker
Each subcontract with value, variations, certified, retention, advance, paid and balance, plus bond and insurance expiry warnings
- How to use
- Register
- Register (SAMPLE)