Geotechnical

Retaining Systems & Excavation Support

Any vertical change in ground level needs support, permanently with a retaining wall or temporarily during basement excavation.

Permanent walls

  • Gravity walls (mass concrete, gabions) resist by their weight.
  • Cantilever RC walls resist through the base slab and heel.
  • Check sliding, overturning, bearing and overall stability, plus drainage behind the wall.

Temporary and embedded support

  • Sheet piles: quick, reusable, good in soft ground and water; vibration and noise need control.
  • Contiguous and secant piles: bored piles in a line; secant piles interlock to cut off water.
  • Diaphragm walls: deep, stiff and watertight, often part of the permanent basement.
  • Support by struts, raking props or ground anchors; anchors may need neighbours' consent.

Earth pressure basics

  • Active pressure when the wall moves away from the soil (lowest).
  • At-rest pressure for walls that cannot move, such as propped basement walls.
  • Passive pressure when the wall pushes into the soil (highest); used for embedment resistance.
  • Water pressure often exceeds soil pressure: drainage design is as important as the wall.
Good to knowInstall monitoring (settlement points, inclinometers, crack gauges) on neighbouring buildings before excavation starts, so you have baseline readings.