Recording Drawing Revisions with Dates: Your Evidence for Claims
Claims are won on dates. A tidy log of when each drawing revision was needed, received and acted on turns 'the design kept changing' into evidence an engineer or tribunal can accept.
Record for every revision
- Drawing number, revision and the designer's issue date.
- Date received by you and the transmittal or letter reference: the received date matters more than the issue date.
- Date needed: when the programme needed this information (from the information required schedule or the activity start minus lead time).
- What changed: clouded areas, a short description and the affected work.
- Status of that work when the revision arrived: not started, in progress, completed (abortive work), materials ordered or delivered.
- Links: the RFI or site instruction behind it, the notice you sent and its date.
How the log supports a claim
- Late information: received date − needed date = days of potential delay for that activity; on the critical path it supports an extension of time.
- Variations: the change from the contract drawing, with dates, supports a variation for added or changed work.
- Abortive work: work completed before the revision arrived, plus materials already bought, supports a cost claim.
- Disruption: many revisions on the same area over a short time show why productivity fell.
- Time bars: the received date starts the notice period in many contracts; the log shows your notice was in time.
A short example
- The programme needed the MEP riser IFC on 1 March. Rev C02 arrived on 25 March with the risers moved, after 40 % of the sleeves were cast. The log shows 24 days late information, abortive sleeves and a notice sent on 3 April (9 days after receipt, inside a 28-day period). That record, plus the programme update, is the core of the claim.
Note
- General guidance, not legal advice. Entitlement depends on your contract; read the clauses on information, variations and notices.