Recording Drawing Revisions with Dates: Your Evidence for Claims

Claims are won on dates. A tidy log of when each drawing revision was needed, received and acted on turns 'the design kept changing' into evidence an engineer or tribunal can accept.

Record for every revision

  • Drawing number, revision and the designer's issue date.
  • Date received by you and the transmittal or letter reference: the received date matters more than the issue date.
  • Date needed: when the programme needed this information (from the information required schedule or the activity start minus lead time).
  • What changed: clouded areas, a short description and the affected work.
  • Status of that work when the revision arrived: not started, in progress, completed (abortive work), materials ordered or delivered.
  • Links: the RFI or site instruction behind it, the notice you sent and its date.

How the log supports a claim

  • Late information: received date − needed date = days of potential delay for that activity; on the critical path it supports an extension of time.
  • Variations: the change from the contract drawing, with dates, supports a variation for added or changed work.
  • Abortive work: work completed before the revision arrived, plus materials already bought, supports a cost claim.
  • Disruption: many revisions on the same area over a short time show why productivity fell.
  • Time bars: the received date starts the notice period in many contracts; the log shows your notice was in time.

A short example

  • The programme needed the MEP riser IFC on 1 March. Rev C02 arrived on 25 March with the risers moved, after 40 % of the sleeves were cast. The log shows 24 days late information, abortive sleeves and a notice sent on 3 April (9 days after receipt, inside a 28-day period). That record, plus the programme update, is the core of the claim.

Note

  • General guidance, not legal advice. Entitlement depends on your contract; read the clauses on information, variations and notices.
Good to knowLog the revision the day it arrives, not when the claim starts. Dates written later are easy to challenge.

Use with this guide

Free

Drawing Revision & Impact Log

Every revision with issue, received and needed dates, days late, what changed, status of affected work, abortive work, RFI / instruction links and notice due / sent warnings

  • How to use
  • Log
  • Log (SAMPLE)

Excel (.xlsx) · version 1.0 · revised 21 Nov 2026 · blank template with a filled sample · check it against your project specification

ChecklistWhen a New Drawing Revision ArrivesTopicNotices and Time Bars: Why the Deadline MattersTopicExtension of Time and Claims: the Basics
Found an error? Tell us

Describe the problem briefly (the wrong value, the right one, and the reference if you have it). The page name is sent automatically.