Water & wastewater

Pumping Stations

Where gravity can't carry flow further, a pumping station lifts it into a rising main. Pumping stations are where networks fail most often, so reliability, access and safety drive the design.

Layout and sizing

  • Duty and standby pumps (e.g. 1+1 or 2+1), each able to carry the peak flow with one unit out of service.
  • Wet well volume set so pumps don't start too often; manufacturers give a maximum number of starts per hour.
  • Screens or macerators protect pumps; valve chambers hold non-return and isolating valves.
  • An emergency overflow or storage and a standby generator, as the authority requires.

Rising mains

  • Sized for a velocity that keeps solids moving but limits head loss (often around 0.75–2 m/s; check the standard).
  • Surge (water hammer) from pump trips must be checked and controlled.
  • Air valves at high points; long rising mains with sewage generate H2S at the discharge.

Controls and safety

  • Level control with duty rotation, high-level alarm and telemetry (SCADA) to the operator.
  • Ventilation and gas detection; wet wells are confined spaces.
  • Lifting equipment and safe access for pump removal.
  • Commission with real flow: pump curves, currents, levels, alarms and the standby switchover.
Good to knowTest the standby pump and the generator switchover with the station full, not just with clean water at a low level.