Project Stages by Drawings: From Tender to As-built
A project moves through a chain of drawings. Each set has a purpose, an author and a status, and each change between sets can move time and money. Knowing the chain tells you what to build from, what to ask for, and what to record.
1. Tender and contract drawings
- Issued by the employer's designer with the tender. Your price and programme are based on them.
- On award, freeze the exact list (numbers, revisions, dates) as the contract drawings. Every later change is measured against this baseline.
- Note gaps and conflicts found at tender (tender queries); they often become the first RFIs.
2. Construction issue (IFC) drawings
- Issued for construction by the designer (or by you, in design-and-build after approval).
- Compare each IFC with the contract drawing: any difference in scope, size, quantity or level is a potential variation.
- Record the date each IFC was received against the date the programme needed it.
3. Shop drawings and coordination
- Prepared by the contractor or specialist: exact sizes, routes, fixings, equipment from approved submittals.
- Combined services and builder's work drawings resolve clashes between trades before work starts.
- Submitted for approval with a transmittal; consultant codes (A, B, C) and dates recorded for each revision.
4. Changes during construction
- New revisions, sketches, site instructions and RFI answers change the work. Each arrives on a date and may affect work already done.
- Check every new revision the day it arrives: what changed (clouds), where, and whether that work is done, in progress or not started.
- If it changes scope, time or cost: notify under the contract within the notice period.
5. As-built and record drawings
- Prepared from site mark-ups: what was actually installed, with final routes, levels and equipment tags.
- Checked, signed and handed over with the O&M manuals; utility owners and authorities often need their own format.
- As-builts also show what changed from the contract drawings, which supports the final account.