Site practice

Drawing & Document Control

Most site mistakes that cost real money start with someone building from the wrong revision. Document control makes sure everyone has the latest approved drawing, knows what it may be used for, and can prove what was sent and when.

Revisions and status

  • Every drawing carries a revision (e.g. P01, P02 for preliminary; C01 for construction) and a revision table describing the change.
  • A status or suitability code shows what it may be used for: for information, for coordination, for approval, for construction, as-built.
  • Consultant review codes (e.g. A approved, B approved with comments, C revise and resubmit) are recorded against each submission.
  • Only drawings marked for construction go to the site teams.

Registers and transmittals

  • A drawing register lists every drawing and revision with its status and date.
  • Every issue goes with a transmittal: what was sent, to whom, why and when a reply is due.
  • Track overdue replies weekly; they delay approvals and procurement.
  • Keep a log of incoming drawings from the consultant and other trades too.

On site

  • Withdraw and stamp superseded prints as soon as a new revision arrives; keep one controlled set.
  • Mark-ups of site changes are collected continuously for the as-built drawings, not at the end.
  • QR codes or a CDE app on tablets help supervisors check they have the latest revision.
  • As-builts are verified, signed and handed over with the O&M manuals.
Good to knowAsk every foreman once a week: 'Which revision are you working from?' If the answer isn't on the register as LATEST, stop and replace the drawing.