Quality & Site Records: NCRs, RFIs, Submittals and Revisions
Good records decide inspections, payments and claims. Four registers carry most of the weight on site: submittals, RFIs, NCRs and drawing revisions. Each one needs a number, a status, a date and an owner.
Submittals
- Number each submittal and keep the revision with it (Rev 0, 1, 2…). A resubmission is a new revision, not a new number.
- Status codes are set by your contract; a common pattern is A approved, B approved as noted, C revise and resubmit, D rejected.
- Never order or install against a C or D status. B means you may proceed but must incorporate the comments.
- Track the review period from the contract and chase before it expires, not after.
RFIs
- One question per RFI, with the drawing or spec reference and a proposed solution where you can.
- Record whether the answer may affect cost or time: that is the first step of a variation or claim.
- Close the RFI only when the answer is received and distributed to the people building the work.
- Answers that change the design should come with revised drawings or an instruction, not only an RFI reply.
NCRs and corrective action
- Describe the non-conformance against a requirement (spec clause, drawing, ITP line).
- Correction fixes this case; corrective action removes the root cause so it does not happen again. Both are needed.
- Close the NCR only after re-inspection and evidence that the corrective action works.
- Review the NCR log monthly: repeating categories show where training or procedures need to change.
Revision control
- Only the latest approved revision goes to site. Stamp or watermark superseded copies and withdraw them.
- Keep a drawing register with the current revision and its date; check it before every inspection.
- Record which revision each inspection, test and as-built was based on.
Common submittal status codes (example)
| Code | Meaning | Can you proceed? |
|---|---|---|
| A | Approved | Yes |
| B | Approved as noted | Yes, include the comments |
| C | Revise and resubmit | No |
| D | Rejected | No |
Use with this guide
Submittal & RFI Tracker
Two registers with status codes, due dates, days open and overdue flags
- How to use
- Submittal register
- RFI register
NCR & Corrective Action Log
NCR form with root cause and corrective action, plus a log with overdue flags
- How to use
- NCR form
- NCR form (SAMPLE)
- NCR log