BIM Basics (ISO 19650)
BIM (building information modelling) is not just a 3D model: it is a way of managing information so everyone works from the same, current, checked data. ISO 19650 sets out how that information is requested, produced, shared and handed over.
Requirements and plans
- The client sets out what it needs: organisational (OIR), asset (AIR), project (PIR) and exchange information requirements (EIR).
- The delivery team answers with a BIM execution plan (BEP): roles, software, standards, naming, model breakdown and delivery dates.
- A responsibility matrix and a master information delivery plan (MIDP) list who delivers which information and when.
Common data environment (CDE)
- One CDE holds all project information with four states: Work in progress, Shared, Published and Archived.
- Information moves from WIP to Shared only after a check, and to Published only after approval.
- Suitability codes (e.g. S1 for coordination, S3 for review and comment, S4 for stage approval) show what a shared file may be used for.
- Naming follows a fixed pattern (project–originator–volume–level–type–role–number), so files sort and search reliably.
Level of detail and information
- LOD (geometry) and LOI (data) grow through the stages: from massing to construction detail and as-built.
- Agree in the BEP what each model element must contain at each stage, instead of 'LOD 400 for everything'.
- At handover, the asset information model (AIM) feeds facilities management: equipment data, O&M links and maintenance requirements.
- Many Gulf clients now include BIM requirements in contracts; read them before pricing.
CDE states
| State | Meaning |
|---|---|
| Work in progress | Being produced by one team; not for others to use |
| Shared | Checked and released to others for coordination |
| Published | Approved for a specific use, e.g. construction |
| Archived | Record of what was shared and published, kept for audit |