Pressure Relief & Overpressure Protection
A relief valve is the last line of defence when control and trips have failed. It only works if it was sized for the right scenario, set correctly, installed with clear inlet and outlet, and maintained.
Scenarios
- Every vessel or system that can be overpressured needs protection. API 521 lists the scenarios.
- Common cases: blocked outlet, external fire, control-valve failure, loss of cooling, tube rupture in an exchanger, and thermal expansion of trapped liquid.
- Each scenario gives a relieving rate; the largest governs the valve size, and the flare or vent system must take it.
Set pressure and accumulation
- The set pressure of the first valve is at or below the MAWP of the protected equipment.
- Accumulation is the pressure rise above MAWP while relieving: commonly 10 % for a single valve, 16 % for several valves and 21 % for fire.
- Pilot-operated and balanced bellows valves are used where back pressure is high or variable.
Installation and maintenance
- Keep the inlet pressure loss below about 3 % of set pressure to avoid chattering (API 520 Part II).
- Outlets go to a flare header or a safe location; never point them at walkways or into buildings.
- Isolation valves under relief valves are locked or car-sealed open (CSO) and controlled by permit.
- Valves are bench-tested and recertified at set intervals; the tag shows set pressure and test date.
Typical allowable accumulation (ASME VIII / API 520)
| Case | Above MAWP |
|---|---|
| Single valve, non-fire | 10 % |
| Multiple valves, non-fire | 16 % |
| Fire case | 21 % |