Material Samples and Mock-ups: When and Why
A data sheet shows what a product should be; a sample shows what you will actually get. Once the consultant approves a sample, it becomes the standard that every delivery is checked against until handover.
When a sample is required
- The specification asks for it: read the submittals or samples clause of each specification section. If samples are listed, submit them even when the data sheet is already approved.
- Appearance matters: colour, finish or texture that a data sheet cannot show. In electrical work: light fittings, switch and socket plates, exposed trunking, floor box covers.
- The client or architect must choose: colour, finish or fitting style.
- You propose an alternative to the specified make: the consultant usually wants to compare it physically.
- The consultant asks in the review comments: 'submit sample for approval'.
- Bulk items where quality must stay the same: cables and their printed markings, cable tray and fittings, glands, earthing clamps.
Why it matters
- The approved sample is the reference standard: a supplier cannot quietly deliver a cheaper version.
- It finds problems before ordering and installing. Rejecting one fitting costs little; rejecting 500 installed ones means removal at your cost or a dispute.
- It settles arguments about appearance with a physical comparison instead of opinions.
- It is evidence at inspection and handover that what was installed is what was approved.
How samples are handled
- Submit with a transmittal that quotes the material submittal reference; send the number of pieces the specification asks for, usually two or three.
- Label every piece: project, item, make and model, submittal number, date.
- The consultant signs or stamps the approved pieces. One stays in the site sample room, locked, until handover; one comes back to you; one may go to the supplier.
- Check every delivery against the approved sample and record it on the delivery inspection.
- A rejected sample is a code C or D: answer the reasons in a Comment Response Sheet before sending a new one.
Mock-ups
- A mock-up is a sample at full scale: a typical room, a ceiling bay with its light fittings, a façade lighting section or a typical riser.
- It is built in its final position or in a separate area, inspected by the consultant and client, and approved before the work is repeated across the project.
- It shows interfaces between trades (ceiling, lighting, sprinklers, diffusers) that no single submittal shows.
- Keep the approved mock-up untouched, or photograph and document it, as the standard for the rest of the work.
Timing
- Do not wait for the data sheet approval to arrange samples: imported samples can take weeks and hold up the whole item.
- Plan samples and mock-ups in the submittal programme, before the latest order date for the material.
Use with this guide
Material Sample Register
Every sample and mock-up with its submittal reference, dates, approval code, sample room location and delivery checks, with counts of pending, overdue and rejected samples
- How to use
- Register
- Register (SAMPLE)
Comment Response Sheet (CRS)
Every reviewer comment with your response, action, revision and status, with counts of open and disputed comments and a ready-to-resubmit check
- How to use
- CRS
- CRS (SAMPLE)