Material Samples and Mock-ups: When and Why

A data sheet shows what a product should be; a sample shows what you will actually get. Once the consultant approves a sample, it becomes the standard that every delivery is checked against until handover.

When a sample is required

  • The specification asks for it: read the submittals or samples clause of each specification section. If samples are listed, submit them even when the data sheet is already approved.
  • Appearance matters: colour, finish or texture that a data sheet cannot show. In electrical work: light fittings, switch and socket plates, exposed trunking, floor box covers.
  • The client or architect must choose: colour, finish or fitting style.
  • You propose an alternative to the specified make: the consultant usually wants to compare it physically.
  • The consultant asks in the review comments: 'submit sample for approval'.
  • Bulk items where quality must stay the same: cables and their printed markings, cable tray and fittings, glands, earthing clamps.

Why it matters

  • The approved sample is the reference standard: a supplier cannot quietly deliver a cheaper version.
  • It finds problems before ordering and installing. Rejecting one fitting costs little; rejecting 500 installed ones means removal at your cost or a dispute.
  • It settles arguments about appearance with a physical comparison instead of opinions.
  • It is evidence at inspection and handover that what was installed is what was approved.

How samples are handled

  • Submit with a transmittal that quotes the material submittal reference; send the number of pieces the specification asks for, usually two or three.
  • Label every piece: project, item, make and model, submittal number, date.
  • The consultant signs or stamps the approved pieces. One stays in the site sample room, locked, until handover; one comes back to you; one may go to the supplier.
  • Check every delivery against the approved sample and record it on the delivery inspection.
  • A rejected sample is a code C or D: answer the reasons in a Comment Response Sheet before sending a new one.

Mock-ups

  • A mock-up is a sample at full scale: a typical room, a ceiling bay with its light fittings, a façade lighting section or a typical riser.
  • It is built in its final position or in a separate area, inspected by the consultant and client, and approved before the work is repeated across the project.
  • It shows interfaces between trades (ceiling, lighting, sprinklers, diffusers) that no single submittal shows.
  • Keep the approved mock-up untouched, or photograph and document it, as the standard for the rest of the work.

Timing

  • Do not wait for the data sheet approval to arrange samples: imported samples can take weeks and hold up the whole item.
  • Plan samples and mock-ups in the submittal programme, before the latest order date for the material.
Good to knowPhotograph every approved sample next to its label. If the physical sample is lost or damaged, the photo and the signed transmittal still prove what was approved.

Use with this guide

ChecklistMaterial Sample Submission
Free

Material Sample Register

Every sample and mock-up with its submittal reference, dates, approval code, sample room location and delivery checks, with counts of pending, overdue and rejected samples

  • How to use
  • Register
  • Register (SAMPLE)

Excel (.xlsx) · version 1.0 · revised 21 Nov 2026 · blank template with a filled sample · check it against your project specification

TopicMaterial Submittals from A to ZChecklistMaterial Submittal Package
Free

Comment Response Sheet (CRS)

Every reviewer comment with your response, action, revision and status, with counts of open and disputed comments and a ready-to-resubmit check

  • How to use
  • CRS
  • CRS (SAMPLE)

Excel (.xlsx) · version 1.0 · revised 21 Nov 2026 · blank template with a filled sample · check it against your project specification

TopicResponding to Consultant Comments and Resubmitting
Found an error? Tell us

Describe the problem briefly (the wrong value, the right one, and the reference if you have it). The page name is sent automatically.