Material Submittals from A to Z
A material cannot be ordered until it is approved, and approval often takes longer than delivery. Plan submittals backwards from the date the material is needed on site.
The usual order
- Prequalification of the vendor → material submittal → shop drawings → samples → mock-up → order → inspection on delivery.
- Date needed on site − delivery − manufacturing − approval cycles (allow for at least one resubmission) = latest submission date.
A complete package
- Cover sheet with specification sections, BOQ items, drawings and where the material is used.
- Compliance statement clause by clause, data sheets with the model highlighted, certificates and test reports.
- Selection calculations where the choice depends on them (cable size, pump duty, breaker rating).
- Warranty, origin and lead time.
Alternatives ('or equal')
- Show equal or better performance clause by clause, plus the reason (availability, lead time, cost).
- An approved alternative that costs the employer less may be shared as a saving; one that costs more is usually yours unless instructed.
- Never install before approval: removal is at your cost.
Use with this guide
Material Sample Register
Every sample and mock-up with its submittal reference, dates, approval code, sample room location and delivery checks, with counts of pending, overdue and rejected samples
- How to use
- Register
- Register (SAMPLE)
Specification Compliance Statement
Clause by clause: specified requirement, offered, complies / deviation / not applicable, reference in the data sheet, with a summary of deviations for the submittal
- How to use
- Compliance
- Compliance (SAMPLE)
Submittal & RFI Tracker
Two registers with status codes, due dates, days open and overdue flags
- How to use
- Submittal register
- RFI register