Levelling & Height Control
Levels decide whether drainage flows, slabs are flat and lifts arrive at the right floor. Levelling is simple, which is why its errors are usually blunders: a misread staff, a wrong benchmark or an unchecked instrument.
The basics
- A benchmark (BM) has a known level; temporary benchmarks (TBMs) are set around site from it.
- Backsight (BS) to a known point, foresight (FS) to the next; reduced level = previous level + BS − FS (rise and fall, or height of collimation).
- Keep backsight and foresight distances roughly equal to cancel collimation and curvature errors.
Closing and checking
- Always close a run on a known benchmark or back on the start; never leave a run open.
- Compare the misclosure with the allowable value (often ± c √K mm, with c from the specification) and distribute it if accepted.
- Arithmetic check: ΣBS − ΣFS = last level − first level.
- Do a two-peg test regularly to check the level's collimation; record the result.
On site
- Protect TBMs from traffic and excavation, and re-check them against the main benchmark regularly.
- Read the staff carefully (metric E-face staffs are easy to misread by 0.1 m); digital levels remove most reading errors.
- Hand the levels to the trades as marked points with written values, not by phone.