Process & industrial

Hazardous Areas & Ex Equipment

Where flammable gas, vapour or dust can be present, electrical and instrument equipment must not become a source of ignition. For electrical engineers on process jobs, this is the topic that changes every equipment choice.

Area classification

  • Done by the process and safety team to IEC 60079-10-1 (gas) or 60079-10-2 (dust), shown on hazardous-area drawings.
  • Zone 0: explosive atmosphere present continuously or for long periods. Zone 1: likely in normal operation. Zone 2: unlikely, and only briefly.
  • Dust uses Zones 20, 21 and 22 with the same logic.
  • Ventilation, release rates and grade of release set the zone extents.

Choosing equipment

  • Equipment protection level: Ga for Zone 0, Gb for Zone 1, Gc for Zone 2.
  • Gas group: IIA (e.g. propane), IIB (e.g. ethylene), IIC (hydrogen, acetylene). IIC equipment also suits IIB and IIA areas.
  • Temperature class: the hottest surface must stay below the gas's ignition temperature.
  • Protection concepts: Ex d flameproof, Ex e increased safety, Ex i intrinsic safety, Ex p pressurised, Ex m encapsulated. Certificates are IECEx or ATEX.

Installation and inspection

  • Install to IEC 60079-14: certified cable glands matching the enclosure, correct sealing, earthing and bonding.
  • Keep the Ex certificate and the equipment's special conditions (the "X" suffix) in the dossier.
  • Inspect to IEC 60079-17: initial detailed inspection, then periodic visual, close or detailed inspections.
  • Many Gulf oil and gas owners require IECEx-certified equipment and competent persons (IECEx CoPC).

Temperature classes (IEC 60079-0)

ClassMax. surface temperature
T1450 °C
T2300 °C
T3200 °C
T4135 °C
T5100 °C
T685 °C
Good to knowOne wrong gland or a missing stopping plug turns an Ex d enclosure into ordinary equipment. Inspect the details, not just the nameplate.