Fire protection

Gas Suppression & Special Hazards

Where water would cause as much damage as the fire (data centres, control rooms, archives, switchgear), rooms are protected by gas that floods the space and puts the fire out without leaving residue.

Agents

  • Clean agents (NFPA 2001 / ISO 14520): halocarbons such as HFC-227ea and FK-5-1-12, and inert gases such as IG-541 or IG-55.
  • Halocarbons extinguish mainly by absorbing heat; inert gases by lowering the oxygen level.
  • CO₂ is effective but lethal at extinguishing concentrations: only for unoccupied spaces, with strict safety measures.
  • Check each agent's safe exposure level for occupied rooms (NOAEL) and its environmental profile.

Design

  • Agent quantity comes from the room volume, minimum temperature and the listed design concentration for the hazard (see the calculator).
  • Detection (often cross-zoned or very early smoke detection) triggers a pre-discharge alarm and a delay so people can leave.
  • Room integrity matters: the room must hold the concentration for the hold time, usually 10 minutes.

Commissioning

  • Door fan (room integrity) test to prove the room is tight enough; seal cable and pipe penetrations, raised floors and ceilings.
  • Check cylinders (weight or pressure), nozzles, pipe supports, abort and manual release, and interfaces (HVAC shut-down, damper closure, power shut-off).
  • Train the operators and post the warning signs and instructions at each door.
Good to knowSeal the room before the integrity test, not after it fails. Most failures are open cable penetrations above the ceiling or under the raised floor.