Formwork, Falsework & Temporary Works Control

Formwork shapes the concrete; falsework holds it up until it can carry itself. Both are temporary works, and most collapses happen because nobody checked them against the design before loading or striking.

Temporary works control

  • A procedure based on BS 5975 names a temporary works coordinator (TWC) and supervisors (TWS) for each area.
  • Every item has a design brief, a design with the right level of independent check, and a register entry.
  • A permit to load is signed before concrete is poured on falsework, and a permit to strike before it is removed.
  • Changes on site (different props, missing bracing) go back to the designer, never improvised.

Formwork

  • Fresh concrete pushes on wall and column forms like a fluid; pressure depends on pour rate, height and temperature (CIRIA Report 108 is a common method).
  • Ties, walers and soldiers must match the design spacing.
  • Release agent, joints and cover spacers checked before the pour; the pre-pour checklist signed.

Falsework and striking

  • Props and towers plumb, on adequate bases, braced as designed; check loads from the slab above plus construction loads.
  • Back-propping carries new slabs through floors that are not yet strong enough.
  • Striking times depend on concrete strength gain (cube or maturity results), not only on days; hot weather speeds early strength but needs good curing.
  • Never strike in a different sequence from the design.
Good to knowNo signed permit to load, no concrete. It is the cheapest insurance on any structure.