Curtain Walls & Cladding Systems

The façade keeps out sun, heat, wind, rain and sand, and it is one of the most expensive and most visible packages on a building. Most of its problems are decided at the design and submittal stage, long before the first panel arrives.

System types

  • Stick system: mullions and transoms assembled on site, then glazed. Flexible, but quality depends on site work.
  • Unitised system: factory-made panels, usually a floor high, hung from brackets on the slab edge. Faster and better controlled; needs crane or hoist access and careful interface design.
  • Rainscreen cladding (metal, stone, ceramic, fibre-cement panels) on a ventilated cavity over an insulated backing wall.
  • Point-fixed (spider) glazing, shopfronts and louvres complete most façades.

Performance specification

  • Structural: wind loads from the wind study, deflection limits, dead load, building movements (inter-storey drift, slab deflection).
  • Air and water tightness at stated test pressures; thermal performance (U-value, SHGC) and condensation risk.
  • Acoustics, blast or security where required, and fire performance of every material and cavity barrier.
  • Maintenance and access: building maintenance unit (BMU), cleaning, glass replacement.

Interfaces and submittals

  • Brackets and embeds are set by the structure: get their positions and tolerances fixed early.
  • Shop drawings, structural calculations, thermal and condensation reports, samples and a mock-up go through approval before fabrication.
  • Interfaces with roofing, waterproofing, MEP (louvres, lighting) and fire stopping at slab edges are where leaks and fire gaps happen.
Good to knowSurvey the slab edges before fabricating brackets. Concrete is rarely where the drawings say, and unitised panels have very little adjustment.