Trenchless Methods: HDD, Microtunnelling and Pipe Jacking

Crossing a busy road, a channel or a cluster of services by trench may cost more in diversions and permits than a trenchless crossing.

Main methods

  • Horizontal directional drilling (HDD): a steerable pilot bore, reamed and pulled back with the pipe. Suits pressure pipes and ducts; poor for gravity lines that need an exact fall.
  • Microtunnelling: a remote-controlled boring machine pushing jacking pipes; accurate line and level, suits gravity sewers.
  • Pipe jacking / auger boring: pipes pushed from a thrust pit, usually for shorter, straight crossings.
  • Pipe bursting / relining: replacing or lining an old pipe along its existing route.

What decides the method

  • Gravity or pressure line, diameter and length of the crossing.
  • Ground conditions and groundwater from the site investigation.
  • Space for entry and exit pits or launch and reception shafts.
  • Depth needed below the obstacle and the clearance to existing services.

Risks to manage

  • Drilling fluid escaping to the surface (frac-out) under roads or into water.
  • Hitting unknown services: locate and trial-pit every known crossing first.
  • Settlement or heave of the road; agree monitoring with the road owner.
  • Pipe overstressed during pull-back; check the pipe maker's safe pulling load.
Good to knowAsk for the as-drilled profile of every crossing. It is the only record of where the pipe really is.