Structured Cabling
Structured cabling is the standard copper and fiber network that carries data, voice, CCTV, access control and Wi-Fi in a building. It follows TIA-568 or ISO/IEC 11801 and is usually covered by a manufacturer warranty after certification testing.
The layout
- Backbone: fiber (and sometimes copper) from the main equipment room to each floor's telecom room.
- Horizontal: copper from the floor patch panel to each outlet. The permanent link is limited to 90 m, and the full channel with patch cords to 100 m.
- Labelling to TIA-606 on both ends of every cable, and bonding of racks and trays to TIA-607.
Installation rules
- Bend radius of at least 4 × cable diameter for UTP; avoid tight cable ties, use hook-and-loop straps.
- Keep separation from power cables as required by EN 50174-2 or TIA-569.
- Use one manufacturer's components end to end if you want the system warranty.
- Use one wiring scheme (T568A or T568B) on the whole project.
Certification tests
- A certification tester (e.g. Level IIIe for Cat6A) checks wire map, length, insertion loss, NEXT, PS NEXT, return loss, ACR-F, delay and skew.
- Test every permanent link and keep the native result files: the manufacturer needs them for the warranty.
Copper categories
| Category | Bandwidth | Ethernet on 100 m |
|---|---|---|
| Cat5e | 100 MHz | 1 Gb/s |
| Cat6 | 250 MHz | 1 Gb/s (10 Gb/s up to about 55 m) |
| Cat6A | 500 MHz | 10 Gb/s |
| Cat8 | 2000 MHz | 25/40 Gb/s up to 30 m (data centres) |