Managing Subcontractors: Award to Final Account

Most of the work on a building or infrastructure project is done by subcontractors. Their performance, payments and paperwork decide the main contractor's progress and margin.

Award

  • Compare like with like: same scope, exclusions and terms (Supplier Quotation Comparison works for subcontract offers too).
  • Back-to-back terms: notices, programme, payment and defects obligations at least as strict as the main contract.
  • Check capacity, current workload, insurances and approvals needed from the client.

Every month

  • Valuation of work done, approved variations, retention and advance recovery; pay on time to keep priority.
  • Track bonds and insurance expiry dates.
  • Record their manpower, delays and back-charges with dates.

Close-out

  • Final measurement, variations and back-charges agreed; final account signed (Subcontract Final Account Closing).
  • Retention and bonds released on the agreed dates.
Good to knowPay good subcontractors on time. On a busy market, the one paid on time sends the best gang to your site.

Use with this guide

Free

Subcontractor Register & Payment Tracker

Each subcontract with value, variations, certified, retention, advance, paid and balance, plus bond and insurance expiry warnings

  • How to use
  • Register
  • Register (SAMPLE)

Excel (.xlsx) · version 1.0 · revised 21 Nov 2026 · blank template with a filled sample · check it against your project specification

ChecklistSubcontractor OnboardingChecklistSubcontract Final Account ClosingCalculatorInterim Payment Application (Net Due)
Found an error? Tell us

Describe the problem briefly (the wrong value, the right one, and the reference if you have it). The page name is sent automatically.