Testing and Commissioning Stages

Equipment passes through a series of tests before handover. Each stage proves something the previous one could not.

The sequence

  • FAT: factory acceptance test, witnessed at the manufacturer before shipping.
  • Pre-commissioning: installation checks, insulation resistance, continuity, torque checks.
  • SAT / commissioning: each system energised and tested on site against its design.
  • Load bank testing: generators and UPS tested at full rated load with artificial loads.
  • IST: integrated systems test, where all systems work together under simulated events such as utility failure.
Good to knowAgree test procedures and acceptance criteria with the consultant before testing starts. Rejected tests usually come from unclear criteria, not faulty equipment.