Stakeholder Mapping and the Communication Plan
Projects are delayed as often by people as by ground or design: an authority that was not consulted, a neighbour who complains, a client department nobody spoke to. A simple map and plan prevents most of it.
Map them
- List everyone with an interest: client and its departments, end users, consultant, designers, authorities, utility owners, neighbours, subcontractors, suppliers.
- Place each on a power–interest grid: high power and high interest = manage closely; high power, low interest = keep satisfied; low power, high interest = keep informed; low both = monitor.
- Note what each wants and what they could stop or delay.
Plan the communication
- For each group: what they need, how often, by which channel, and who on your team owns it.
- Use the formal channel the contract sets for contractual matters; meetings and calls are for coordination.
- Keep a stakeholder register and review it monthly; people change roles.