Procurement on Site: Material Request to Delivery
Late material is one of the commonest causes of site delay. A simple tracker from request to delivery shows what is at risk weeks before it stops the work.
The chain
- Material request (from the programme and approved submittal) → quotations (at least three where possible) → comparison and approval → purchase order → expediting → delivery → receiving inspection → store.
- Each step has a date; the date needed on site drives everything.
Comparing quotations
- Same specification and quantity; check compliance with the approved submittal.
- Compare total landed cost: price, delivery, taxes and duties, payment terms, validity, warranty, lead time.
Receiving
- Check against the order and delivery note; inspect quality (Material Receiving Inspection Record).
- Record shortages and damage on the delivery note before signing.
Use with this guide
Purchase Order & Delivery Tracker
Material request to delivery: dates for request, order and needed-on-site, expected and actual delivery, ordered vs received quantity, late and short flags
- How to use
- Tracker
- Tracker (SAMPLE)
Supplier Quotation Comparison
Three quotations side by side: unit rates, totals, delivery, payment terms, validity, compliance and a recommended supplier
- How to use
- Comparison
- Comparison (SAMPLE)
Store Material Register
Item list with live stock balance and reorder flags, a stock movement log, and a sub-store receiving note for material from the main store
- How to use
- Item list
- Stock movements
- Receiving from main store
- Item list (SAMPLE)
- Stock movements (SAMPLE)
- Receiving from main (SAMPLE)
Material Receiving Inspection Record
MIR form, receiving checks and an MIR log with overdue flags
- How to use
- MIR form
- MIR form (SAMPLE)
- MIR log