Inspection & Testing: ITPs, Hold Points and Closing Inspections

Every inspection on site follows a plan: the Inspection and Test Plan (ITP). It says what is checked, against which criteria, who attends and what record proves it. Getting this right avoids rejected inspections, rework and missing records at handover.

1. The ITP

  • Prepared by the contractor for each work package and approved by the consultant before the work starts.
  • Each line lists the activity, the reference (spec clause, standard or drawing), the acceptance criteria, the frequency and the verifying record.
  • Inspection levels are set for each party. The codes below are typical; your contract defines the actual ones.
  • Write acceptance criteria as measurable values (e.g. ≥ 1 MΩ at 500 V DC) rather than 'as per spec'.

2. Material receiving

  • Check every delivery against the approved submittal: make, model, rating, size and quantity.
  • Collect test or mill certificates with the delivery note; missing certificates usually mean the item stays on hold.
  • Inspect condition and storage. Quarantine and label any non-conforming item and raise an NCR.
  • Raise the material inspection request (MIR) and record it in the MIR log.

3. Raising an inspection request

  • Self-inspect first against the ITP line and the latest approved shop drawing.
  • Attach the evidence: checklists, test sheets, calibration certificates, photos.
  • Respect the notice period in your contract (often 24 hours, project-defined).
  • Offer only complete areas. Partial offers are the most common reason for rejection.

4. Closing the inspection

  • Record the result using the project's codes (for example approved, approved with comments, rejected).
  • Close comments and re-offer rejected items with a reference to the original request.
  • File the signed record against the ITP line. At handover, every hold point needs a signed record.
  • Track open requests and their age; overdue requests delay the programme and payment.

Typical inspection levels

CodeMeaningCan work continue?
H · HoldInspector must attend and releaseNo, not until released
W · WitnessInspector is notified and may attendYes, if no attendance after the notice period
R · ReviewDocuments reviewed, no attendanceYes
S · SurveillanceRandom checks at the inspector's choiceYes
Good to knowKeep one inspection log for the whole project with days-open and overdue flags. It is the first thing a good QA/QC manager reviews every morning.

Use with this guide

Free

Material Receiving Inspection Record

MIR form, receiving checks and an MIR log with overdue flags

  • How to use
  • MIR form
  • MIR form (SAMPLE)
  • MIR log

Excel (.xlsx) · version 1.1 · revised 7 Nov 2026 · blank template with a filled sample · check it against your project specification

Free

Store Material Register

Item list with live stock balance and reorder flags, a stock movement log, and a sub-store receiving note for material from the main store

  • How to use
  • Item list
  • Stock movements
  • Receiving from main store
  • Item list (SAMPLE)
  • Stock movements (SAMPLE)
  • Receiving from main (SAMPLE)

Excel (.xlsx) · version 1.0 · revised 12 Nov 2026 · blank template with a filled sample · check it against your project specification

ChecklistInspection ReadinessTemplateRequest for Information (RFI)
Found an error? Tell us

Describe the problem briefly (the wrong value, the right one, and the reference if you have it). The page name is sent automatically.