Lessons from failures

Hyatt Regency Walkway, 1981

Two suspended walkways in a Kansas City hotel atrium collapsed during a crowded event, killing 114 people.

What happened

  • The original design hung both walkways from continuous rods.
  • During shop drawing development, the detail changed to two offset rods. This doubled the load on the upper walkway's beam connection.
  • The connection was already weak in the original design. Under the changed detail, the nut pulled through the beam.

The lesson

  • Any change to a connection or load path needs the engineer of record's calculation, not just a drawing approval.
  • Shop drawing review is an engineering check, not a formality.
Good to knowOn your projects, flag every contractor-proposed change to structural details for a design check.