Authority Approvals and Handover of Utility Networks
Utility networks are built for owners who are not your client: the power, water, drainage, telecom and road authorities. Their approvals decide when the work can start and when it is finished.
Before work starts
- Design approval from each owner, often in stages (concept, detailed).
- No-objection certificates (NOCs) from owners of existing services along the route.
- Permit to dig and traffic management approval for each work zone.
- Approved materials list or submittals for pipes, ducts, cables, covers and fittings.
During the work
- Book the owner's inspections at hold points: before backfill, before pour, before connection.
- Keep the test records, photos and survey of each section as you go.
- Report any damage to existing services at once to its owner.
Handover
- As-built drawings in the owner's format (often with coordinates and levels).
- Test certificates, material certificates and warranties.
- Joint inspection and a closed defects list.
- Taking-over letter from each owner; the defects period starts from it.
Use with this guide
Network Test Tracker by Section
Pressure, air, CCTV, mandrel and compaction tests per section with dates, witness, result and progress per network
- How to use
- Tests
- Tests (SAMPLE)
Utility Crossing & Clash Register
Every crossing and clash by chainage: services, levels, clearance check, owner, solution and status
- How to use
- Register
- Register (SAMPLE)