Facility management

Asset Life Expectancy and Replacement Planning

Every asset has an economic life. A lifecycle (replacement) plan spreads capital costs over the years and avoids surprises when old equipment fails.

Indicative economic life (use CIBSE Guide M and maker data for your plan)

  • Chillers and air handling units: about 15–25 years.
  • Split and packaged air-conditioning units: about 10–15 years.
  • LV switchboards and distribution boards: about 20–30 years.
  • Standby generators: about 20–30 years with good maintenance.
  • UPS units: about 10–15 years; VRLA batteries: about 3–10 years depending on design life and temperature.
  • Pumps: about 15–20 years; BMS controllers and software: about 10–15 years.

Building the plan

  • Start from the asset register: install date, condition score and criticality.
  • Adjust life for climate and use: heat, dust and 24/7 running shorten life in the Gulf.
  • Watch for obsolescence: spare parts and software support often end before the hardware wears out.
  • Review the plan every year with condition surveys and failure history.
Good to knowAsk makers for the 'end of sale' and 'end of support' dates of UPS, BMS, fire alarm panels and VFDs. They often decide the replacement year.

Use with this guide

Free

Asset Register

Every maintainable asset with location, maker data, warranty, criticality and replacement year

  • How to use
  • Asset register
  • Asset register (SAMPLE)

Excel (.xlsx) · version 1.0 · revised 12 Nov 2026 · blank template with a filled sample · check it against your project specification

CalculatorSpare Parts Reorder Point
Free

Store Material Register

Item list with live stock balance and reorder flags, a stock movement log, and a sub-store receiving note for material from the main store

  • How to use
  • Item list
  • Stock movements
  • Receiving from main store
  • Item list (SAMPLE)
  • Stock movements (SAMPLE)
  • Receiving from main (SAMPLE)

Excel (.xlsx) · version 1.0 · revised 12 Nov 2026 · blank template with a filled sample · check it against your project specification

Found an error? Tell us

Describe the problem briefly (the wrong value, the right one, and the reference if you have it). The page name is sent automatically.