Project controls & management

Quantity Surveyor / Contracts Engineer

Measures and values the work, prepares interim payments, prices and negotiates variations, manages subcontract accounts and agrees the final account. On the contractor's side the role protects the margin; on the client's side it protects the budget.

Career path

  1. 1
    Assistant QSTakeoff, measurement for interim payments
  2. 2
    Quantity surveyorValuations, variations, subcontract accounts
  3. 3
    Senior QS / contracts engineerClaims, cost reports, final accounts
  4. 4
    Commercial / contracts managerCommercial strategy, disputes, contract administration

Core skills

Quantity takeoff (POMI, CESMM4, NRM2)Rate build-up and star ratesInterim valuationsVariation and claim managementFIDIC conditions of contractCost reporting and forecastingExcel and takeoff software (e.g. CostX)

Recommended certificates

CertificateIssued byWhen
Local engineer registration (Qatar, Saudi Arabia, Egypt)National authorityEarly career
MRICS (chartered quantity surveyor)RICSSenior
FIDIC contracts training / certified contract managerFIDICMid-career
Certified Cost Professional (CCP)AACE InternationalSenior
Career tipKeep records as if you'll need them in arbitration. Most commercial arguments are won by the side with the better daily records, not the better argument.

Interview questions

How do you value a variation with no similar BOQ item?

Check the contract's valuation rules first. If no rate is comparable, build up a star rate from labour hours, material with wastage and plant, add OH&P where allowed, and support it with quotations; or record the work as dayworks with daily signed sheets if agreed.

What makes a claim notice effective under FIDIC 2017?

It is given within 28 days of becoming aware of the event, describes the event, refers to the clause, and is sent to the Engineer as the contract requires. Late notice can lose the entitlement, so the register should flag it.

How do you check a subcontractor's interim payment?

Measure progress against the subcontract BOQ on site, check variations against instructions, deduct retention, advance recovery and back-charges, and reconcile with the main contract valuation so we never pay for work we haven't been paid for without reason.

Check each certifying body's website for current eligibility and exam requirements.