Contracts & Claims Engineer
Protects the project's contractual position: reviews contracts, issues notices on time, prices and negotiates variations, and prepares or defends delay and cost claims.
Career path
- 1Contracts engineerCorrespondence, notices, variation records
- 2Senior contracts / claims engineerVariation pricing, extension of time submissions
- 3Contracts managerContract strategy, negotiations, subcontract agreements
- 4Commercial director / claims consultantDisputes, adjudication and arbitration support
Core skills
Recommended certificates
| Certificate | Issued by | When |
|---|---|---|
| FIDIC Certified Contract Manager | FIDIC | Early career |
| Member of the Chartered Institute of Arbitrators (MCIArb) | CIArb | Mid-career |
| Certified Forensic Claims Consultant (CFCC) | AACE International | Senior |
| Member of RICS (MRICS) | Royal Institution of Chartered Surveyors | Senior |
Interview questions
What is a time bar and why does it matter?
A contract deadline for giving notice of a claim. Under FIDIC 2017 Sub-Clause 20.2 the notice is due within 28 days of becoming aware of the event; missing it can lose the right to time or money, so notices are tracked carefully.
How do you value a variation?
First with contract rates where the work is similar, then rates adjusted from similar items, and only then new rates built from cost plus a reasonable profit, supported by records, quotations and the agreed method of measurement.
What records support a delay claim?
Contemporary records: updated programmes, daily reports, correspondence and notices, RFIs and their response dates, site instructions, photographs and resource records showing the cause and effect of the delay.
Check each certifying body's website for current eligibility and exam requirements.